Memorial Hospital West Bed Expansion – Construction Update

Memorial Hospital West Bed Expansion – Construction Update

Pembroke Pines, Florida, August 23, 2011

ANF Group, Inc. just completed their 80% AHCA Inspection on the 3rd floor of the Bed Expansion Project at Memorial Hospital West last week with minimal comments. Inspection of the 4th floor is scheduled to take place first week of September. With the exterior done the crew is working hard to complete the painting, floors and installation of the ceiling grid in the interior of the building. Elevators will be ready for temporary use in the next couple of weeks and site work will begin toward the middle of September.

The project is slated for completion November 2011. Assigned to the job are Project are Project Manager Peter Kurszewski and Superintendent John Hughes.

For more information about ANF Group, Inc. please visit the firm’s website at www.anfgroup.com or contact them at info@anfgroup.com.