Pharmacy Upgrade

Plantation General Hospital – USP 797 Pharmacy Upgrade
  • Project Value: $192,611
  • Project Size: 365 GSF
  • Completion Date: 2011
  • Delivery Method: Lump Sum
  • Project Manager: Raul Cornejo
  • Superintendent: Carlos Dixon

 

Scope of Work
The USP 797 Pharmacy Upgrade project at Plantation General Hospital in Plantation, Florida consisted of upgrading the existing IV/Chemotherapy Preparation areas of the pharmacy.  This project included selective demolition, stainless steel tables, wire shelving, doors, glazing, drywall, finishes, plumbing, mechanical, fire protection and electrical work. This is the addition/renovation of approximately 365 GSF.

Project Owner
HCA – Plantation General Hospital
Bryan Miller
401 NW 42nd Ave, Plantation, FL 33317

Project Architect
Gobbel Hays Partners, Inc.
Mark Smith
217 Fifth Avenue North, Nashville, TN  37219